³ÉÈ˶¶Òõ

A16 Springfield Roundabout September update

A view of the current state of A16 Springfield Roundabout

The latest update on the A16 Springfield Roundabout.

What we achieved in August

  • Completed earthworks and drainage in the roundabout centre and the northeast
  • Started excavation of the new road foundation along the A151 East (outside McDonalds)
  • Completed kerbing in the roundabout centre and on the north, south and west splitter islands
  • Completed low voltage power diversion and the BT diversion in the northeast corner

What’s happening in September

  • Start and finish new kerbs in the roundabout centre
  • Seeding of topsoiled verges will commence site wide
  • Install boundary fencing to the southeast and southwest corners of the scheme
  • Begin final road surfacing for the roundabout
  • Continue installing scheme signs site-wide and lighting columns to A151 East

Current/ongoing traffic restrictions and closures

  • 24/7 barriers at the roundabout, with the current single-lane entries and single-lane exits
  • Ongoing narrowed roundabout lanes

Upcoming traffic restrictions and closures

  • Night-time temporary traffic lights as needed for installation of scheme signs and lighting columns
  • Night-time closures for final surfacing starting in late September (dates to be confirmed)

Published: 2nd September 2024