Grantham Southern Relief Road September 2024 update

A view of the progress on the Grantham Southern Relief Road

The latest update on the Grantham Southern Relief Road.

What we achieved in August

Phase Three

  • East side of site – backfill to east abutment / construct crane platform behind east abutment

What's happening in September

Phase Three

  • East side of site – complete crane platform and access track behind east abutment / reinforcement and shuttering to east abutment ballast wall / concrete east abutment ballast wall

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd September 2024