Grantham Market Place August update

The current progress on Grantham Market Place

The latest update on Grantham Market Place.

What we achieved in July

  • Kerbs and concrete base slabs removed from the Conduit Lane carriageway entrance raised table
  • Kerbs re-laid at new levels at Conduit Lane raised table
  • Removed existing brick arched cover to well and replaced with a pre-cast concrete cover slab
  • Asphalt foundation to Market Place
  • Laid new granite cobbles and Yorkstone setts to 420 square metres of Westgate Road, Conduit Lane and the laybys

What’s happening in August

  • Continue laying granite cobbles and Yorkstone setts, including applying jointing material

Current/ongoing traffic restrictions and closures

  • Full road closure of the Market Place and a soft closure on Conduit Lane (access maintained for taxi rank)
  • 24/7 barriers around the whole Market Place construction area (all pedestrian areas are accessible)
  • Access maintained to the footway outside the Conduit Lane Tearooms and the Reflect Recruitment Offices
  • Removed bollards at the top of Butchers Walk for ease of deliveries to businesses
  • Loading areas maintained at the top of Market Place junction with Watergate and on Narrow Westgate

Upcoming traffic restrictions and closures

  • No changes expected

Published: 2nd August 2024